A US import hold needs coordinated documents, release information and a delivery plan. We work with the importer and appointed customs parties within the agreed freight scope to organize the next steps and identify extra handling or waiting costs.
Identify the hold and the evidence needed to close it
Ask the appointed customs representative for the actual notice, affected shipment references, responsible authority and next required action. Track customs decisions, carrier release, terminal availability and warehouse delivery separately, then price the extra work against a dated record.
Compare your options ↓Choose the option that fits
Identify what is stopping the shipment
A US customs hold can delay delivery, but the first useful action is to identify the precise restriction and the party that issued it. Request the notice or status record linked to the entry, bill of lading and container. Record what is being requested and who must respond. Do not assume that every “clearance delay” in a transport tracker means a physical inspection, a seizure or a problem that the trucker can solve.
| Possible blocker | Evidence to request | Party to coordinate with |
|---|---|---|
| Entry data or documents need review | Specific request, affected entry/line and missing information | Importer and appointed customs representative |
| CBP examination or transfer instruction | Examination status, authorised location and movement instructions | Customs representative, responsible CBP office and examination facility |
| Partner Government Agency review | Agency notice and the product or entry lines affected | Importer, filer and the relevant agency |
| Carrier document or payment release | Named outstanding transport document or charge | Contracted carrier or release agent |
| Terminal or facility availability | Cargo-location status, release conditions and pickup requirements | Terminal/facility and the appointed transport provider |
A Partner Government Agency, or PGA, may have a separate admissibility process for regulated goods. For example, FDA entry review can involve document requests, examinations or sampling, and possible detention following review. This is conditional on the product: it is not a reason to add an FDA step to every shipment. Ask which agencies apply to the actual goods and which decisions remain outstanding.
The following workflow is for commercial US imports. It helps organise information and costs; it does not determine legal admissibility. Keep the importer and appointed representative involved in decisions affecting the entry. Use the existing commercial invoice and product-description guides for the underlying records rather than creating a different version each time someone asks a question.
Keep one record for the 8-pallet example
Consider an independent teaching case: ordinary non-hazardous goods from China arrive in one accepted ocean container. The case assumes a CBP examination, no separate PGA hold, no quantity loss and no finding requiring refusal or corrective treatment. Those assumptions simplify the arithmetic; they do not predict a real examination outcome. Every price and operating duration in the case is invented.
| Field | Case input | Reconciliation check |
|---|---|---|
| Pallets | 8, identified P01–P08 | Each pallet contains 20 cartons |
| Cartons | 160, with unique references C001–C160 | 8 × 20 = 160 |
| Sale units | 10 per carton | 160 × 10 = 1,600 |
| Finished pallet dimensions | 1.20 × 1.00 × 1.80 m each | 8 × 2.160 = 17.280 m³ |
| Finished gross weight | 385 kg per pallet, including packing | 8 × 385 = 3,080 kg |
| Records to link | Entry, bill, container, invoice and packing-list references | Keep the same identifiers on notices, work orders and invoices |
The volume is a cargo record, not proof of loading feasibility or a CES charging basis. An examination facility might charge by container, handling unit, labour or another agreed measure. Ask which quantity applies. If goods are unpacked and rebuilt on different pallets, preserve the original mapping and issue an accurate revised packing record before onward delivery.
The importer’s coordinator should keep the current file and an amendment history. An updated product description may clarify an existing invoice, but it should not silently change the goods, origin, quantity or value. Ask the filer how a genuine correction should be submitted and retain the reason for it.
Answer the specific request with traceable evidence
A good response file connects the requested fact to a source document. Start with the notice’s exact request, not a large unstructured attachment bundle. Name the owner of each missing item and its required response time. The table below is a proposed coordination record; it is not a universal list of documents required for every examination.
| Requested clarification | Evidence to assemble | Close-out record |
|---|---|---|
| What is the product? | Model, materials, function and matching specification | Representative confirms the response addresses the request |
| Which goods does the request cover? | Entry line and carton/pallet mapping | Affected quantities reconciled with the packing list |
| What supports the declared transaction? | Applicable invoice, order and requested supporting records | Submitted document version and receipt retained |
| Where is the cargo? | Facility, container and custody reference | Responsible handler confirms location and access |
| What work is authorised? | Examination/transfer instruction and approved handling scope | Authorisation linked to the transport work order |
| What has changed? | Dated correction with reason and original reference | Filer confirms the accepted submission or next action |
Use a short update format: last confirmed event; unresolved request; owner; expected next update; current delivery implication. “Documents sent” is different from “documents received” or “request satisfied”. If evidence has been submitted but no decision is available, report that accurately. Do not tell the receiver the cargo has cleared simply because an email was delivered.
Keep sensitive commercial and identification records in the agreed secure channel with the appointed parties. The public shipment brief can list the document types needed without publishing those records. Ask for confirmation before booking paid corrective work so the buyer understands both the scope and the unresolved outcome.
Confirm the examination transfer and applicable local instructions
19 CFR 151.15 addresses permission and bonded movement to a Centralized Examination Station, or CES; the port director can specify the movement and facility. Ask the filer to confirm the applicable authorisation, location and responsible carrier. A truck quote or an ordinary release email is not a substitute for that confirmation. Do not instruct a driver to divert held cargo to a convenient warehouse.
Use the instructions for the actual hold and port. Ask the appointed customs representative to confirm the examination facility, required movement authorization, carrier details, response deadline and how that deadline is counted. We coordinate the agreed transport handover after those instructions are clear; a deadline at one port is not a nationwide clearance promise.
The examination work order should identify the shipment, handling units and custody handover. Confirm how broken seals, opened cartons, repacking and revised weights will be recorded. A transfer authorisation concerns moving the goods for the stated purpose; it does not establish release into commerce or a favourable examination result.
Track completion, release and pickup as different events
In this fictional case, normal receipt was planned for Day 2. Day 0 is the point when the examination notice reaches the coordinator. The examined shipment is received on Day 6. These are invented elapsed calendar-day points, not official processing times. Work does not automatically happen on weekends or holidays; a real plan needs dates, operating hours and time zones.
| Point | Case event | What is still required |
|---|---|---|
| Day 0 | Notice recorded and shipment references matched | Clarify the request and assign responses |
| Day 1 | Requested file submitted; applicable transfer arrangements agreed | Actual authorisation and facility acceptance |
| Day 2, 09:00 | Authorised transfer received at the CES | Preparation and examination |
| Day 3 | Handling/preparation completed | Examination and authority’s decision |
| Day 4 | Physical examination completed | Recorded release decision and remaining conditions |
| Day 5 | Hold removed; other release conditions checked | Confirmed truck and receiver appointment |
| Day 6, 09:00 onward | Departure from CES, then warehouse receipt | Count, condition and delivery records reconciled |
Day 6 minus Day 2 is four days later than the original receiving plan. Finishing the physical examination on Day 4 does not make the goods deliverable that day. Nor should the coordinator add every person’s waiting estimate together: some document, payment and appointment work can run in parallel. Use the actual dependency that prevents the next movement.
For the storage calculation below, assume exactly 96 hours from Day 2 at 09:00 to Day 6 at 09:00, charged as four 24-hour blocks with no free period. This is a stipulated billing rule for the example. Do not copy that convention into a tariff that instead counts calendar dates, minimum days or different start and stop events.
Calculate the extra operating bill without double counting
Identify the service provider and agreed payer for examination preparation, package opening and closing, transfer and storage. Have the importer and appointed customs representative confirm applicable obligations and any exception. A facility or trucker’s handling invoice is not automatically a government charge, and there is no single price for all examination work.
The model below counts only incremental operations caused by the examination. Assume the original normal delivery remains in the base freight budget. The extra transfer amount is an agreed addition to that baseline, and the rebooking line covers appointment administration only. Amounts are USD, exclude any applicable tax and use invented rates; none is a CES tariff, CBP fee schedule or VelFreight offer.
| Line | Assumed quantity × rate | Additional amount |
|---|---|---|
| Extra authorised transfer work | One agreed incremental allowance × $420 | 420.00 |
| Facility receiving/handling | 8 pallets × $35 | 280.00 |
| Labour to present cargo | 3 hours × $90 | 270.00 |
| Repacking and package closing | 8 pallets × $25 | 200.00 |
| Facility storage | 8 pallets × 4 blocks × $7.50 | 240.00 |
| Additional coordination service | One agreed task × $95 | 95.00 |
| Receiver appointment rebooking | One administrative change × $85 | 85.00 |
| Incremental subtotal | 420 + 280 + 270 + 200 + 240 + 95 + 85 | 1,590.00 |
The additional allocation is $198.75 per pallet, $9.9375 per carton or $0.99375 per sale unit. These are divisions of one shipment subtotal, not purchasable unit rates. Keep full precision until the invoice allocation is complete. The table excludes duties, the original freight, insurance, penalties, testing or treatment, equipment charges and any additional terminal costs. It is not a landed-cost total.
Request dated charges, authorisation and completion evidence. Check whether labour is already in the facility fee before adding it again. Reconcile the final invoice with actual pallets, hours and storage blocks, and mark an unresolved line as pending rather than zero. The demurrage, detention and storage guide helps identify separate equipment and terminal clocks without confusing them with this facility-storage example.
Test what a longer facility stay changes
Under the invented storage rule, each additional 24-hour block costs 8 × $7.50 = $60. The fixed non-storage part is $1,590 − $240 = $1,350. The sensitivity table changes only facility storage; it does not assume a longer hold has no other operational consequence.
| Billable 24-hour blocks | Storage calculation | Modelled incremental subtotal |
|---|---|---|
| 4, original case | 8 × 4 × $7.50 = $240 | $1,350 + $240 = $1,590 |
| 6, two additional blocks | 8 × 6 × $7.50 = $360 | $1,350 + $360 = $1,710 |
| 9, five additional blocks | 8 × 9 × $7.50 = $540 | $1,350 + $540 = $1,890 |
The extra five blocks add $300 to this limited model. An actual delay may also change chassis use, container free time, labour bookings or delivery charges. Obtain those terms and add them separately. Paying for faster private handling does not guarantee that the authority will complete its decision sooner; confirm precisely what an expedited service can control.
Use a release-to-receipt checklist before dispatch
| Check | Evidence to retain | Remaining risk to close |
|---|---|---|
| Customs decision | Filer confirms current entry status and applicable release | Another unresolved restriction |
| Other agency requirements | Relevant agency status where applicable | A product line still awaiting a decision |
| Carrier and facility conditions | Document, payment and pickup acceptance | Goods released by customs but unavailable to the truck |
| Physical cargo record | Pallet/carton count, seals and repacking notes | Changed packaging not reflected in the delivery file |
| Transport and receiving | Confirmed appointment, vehicle and unloading arrangement | A missed or unsuitable warehouse slot |
| Final receipt | Delivery record, count and condition exceptions | Unexplained difference from the original 160 cartons |
For the example, reconcile eight pallets and 160 cartons before allocating costs across 1,600 sale units. If cartons were opened, identify which were resealed and whether the pallet map changed. Record discrepancies when discovered and preserve the handover evidence; the damage and shortage guide explains the separate claims record.
Send VelFreight the shipment references, current notice, cargo data and receiving requirement for coordination within the agreed service scope. The appointed importer, filer and authorities remain essential to the process. No forwarder can promise to prevent selection for examination or guarantee a release date.
Common US customs-hold questions
Does a customs hold mean the goods have been seized?
The phrase alone does not establish that. Obtain the actual notice, authority, status and required response. Missing data, examination and agency review can require different actions; do not infer an outcome from a short tracking label.
Can I send my normal truck to collect held cargo?
Only arrange the movement that the responsible parties confirm is authorised. A CES transfer can require a particular facility and bonded movement. An ordinary warehouse delivery booking does not satisfy those instructions.
How much will a US customs examination cost?
Request the actual facility and transport rates. The $1,590 example is invented and covers specified additional operations, with taxes and other charges excluded. It is not a federal fee or a nationwide average.
Does selection for examination tell me when the goods will be released?
No. Confirm examination scheduling, completion, authority release and collection readiness separately. We coordinate shipment updates with the importer and appointed representative; a notice or scheduling deadline is not a release commitment.
Can I promise delivery after the examination is finished?
Confirm the release decision and all remaining agency, carrier, facility and appointment conditions first. In the example, the exam finishes on Day 4 but warehouse receipt is on Day 6. Those days illustrate the difference; they are not official service times.
Continue planning with VelFreight: Commercial Invoice Guide: Fields, Worked Example and Checklist →
Example costs and timelines are for planning. Send us your cargo, route and delivery needs for a shipment-specific quote and acceptance review.