VelFreight plans ocean delivery with the release, collection, unloading and empty-return steps in view. Share the booking and receiving requirements early so we can identify free-time questions and the work that could create extra charges.

Ask VelFreight about this shipment ↗
OUR RECOMMENDATION

Identify each clock before counting chargeable days

Ask us to record the applicable free periods, charging events and return arrangements with the delivery plan. We coordinate the agreed release and trucking handovers and flag changes that require a revised appointment or cost decision.

Compare your options ↓

Choose the option that fits

  1. The full container remains at the terminal

    Check the release conditions, terminal storage and carrier equipment-use clock that apply to that booking.

    Before choosing: A customs or document hold does not establish that all charges automatically stop.

  2. The full container has left but is not yet returned empty

    Confirm unloading, the nominated return depot and the accepted return event.

    Before choosing: Warehouse delivery alone may not stop the carrier’s equipment-use clock.

  3. The quote offers combined free time

    Ask how the combined period starts, ends and interacts with storage charges.

    Before choosing: Do not add separate demurrage and detention charges on top of a combined product without checking its terms.

Identify the charge and the party billing it

Demurrage and detention concern the use of carrier equipment beyond the agreed free period, while storage concerns occupation of a terminal, depot or warehouse space. Exact terminology and charging arrangements vary by carrier, location and contract. A carrier may offer separate periods or combined demurrage and detention; storage may be separate or treated within a particular product.

We use the terms and tariff attached to the actual booking when planning delivery. The charge name alone does not tell us the start event, free period, applicable rate or payer. Share the booking confirmation and receiving arrangements so those details can be checked together.

Operational distinction; verify local contractual definitions
ChargeTypical issue to investigateEvidence needed
DemurrageCarrier equipment remains within the specified terminal/depot periodDischarge/gate events and applicable tariff
DetentionCarrier equipment remains outside the defined facility period before returnFull gate-out, empty gate-in and accepted return location
Combined demurrage and detentionOne equipment-use period spans the specified start and return eventsCombined free days, combined rate bands and event definitions
StorageCargo or equipment occupies a separately billed facilityFacility free period, storage basis and release event

Record the exact clock before calculating a charge

Request the start event, end event, included days, free period, weekend/holiday treatment, equipment type, currency and rate bands. Ask whether the first chargeable day is the day after the last free day and whether the return day is counted. Those details can change the number even when the headline daily rate is identical.

Free-time record to save with the booking
FieldExample of a precise entryCheck before using it
Start eventDischarge date or full gate-out dateWhich event is used for this charge
Day conventionCalendar days, event day counted as Day 1Holidays, weekends and partial-day treatment
Free allowanceFive days for this particular chargeTariff or negotiated booking evidence
End eventAccepted empty gate-in at nominated depotNot simply an attempted return
Rate bandsFirst three chargeable days at rate A, later days at BPer container, size/type and currency
Other chargesStorage billed separately or includedAvoid omissions and double counting

The shipper or consignee should know who monitors each clock. The broker may manage clearance, the trucker may manage collection and the warehouse may control unloading, but none of those tasks alone guarantees that someone is watching the return deadline. Assign that monitoring responsibility explicitly.

Check the charging record for your actual booking

We identify the location, equipment, effective terms and event dates before comparing a possible extra charge. A free-time allowance from another route or earlier order is not a reliable basis for the current shipment.

Keep separate records for terminal or warehouse storage and equipment use when both apply. The invented tariff in the next section demonstrates the arithmetic; your actual booking terms determine the payable amount.

The free-time and charging details we check with the shipment
Record to obtainWhat it should identifyHow it supports the delivery plan
Booking and tariff versionEquipment, location, effective period and any agreed free-time termsApplies the correct allowance to the shipment
Start and stop eventsDischarge, availability, gate-out and accepted empty return as relevantShows when each charging clock runs
Calendar conventionWorking or calendar days, holidays and treatment of return dayAvoids miscounting the free and billed days
Charge bands and payerRate units, stepped bands, separate storage and the agreed payerAllows the shipment budget to be reconciled before approval

Use a complete example tariff

The following tariff is invented for calculation training. It is not a live carrier or terminal tariff and does not represent a particular country. It assumes one 40 ft dry container, separate demurrage and detention, calendar days with each start-event day counted as Day 1, and the end-event day counted. The parties must replace every assumption with the actual booking terms.

Illustrative tariff, USD per container per day
ChargeFree periodFirst chargeable bandLater chargeable band
Demurrage5 calendar days from discharge, inclusiveChargeable days 1–3: USD 90/dayChargeable day 4 onward: USD 140/day
Detention4 calendar days from full gate-out, inclusiveChargeable days 1–3: USD 70/dayChargeable day 4 onward: USD 110/day
Terminal storage3 calendar days from discharge, inclusiveUSD 35/day thereafterSame USD 35/day

Storage is deliberately separate in this exercise so that its independent clock is visible. Do not add it to an actual invoice when that storage is already covered by another paid line. Similarly, this separate-clock example cannot be applied to a combined free-time offer.

Calculate discharge, collection and return day by day

Assume discharge on 1 November, full-container gate-out on 9 November and accepted empty return on 16 November. These dates are fictional and carry the counting conventions stated above. Demurrage free days are 1–5 November; chargeable days are 6–9 November. Detention free days are 9–12 November; chargeable days are 13–16 November. Storage is charged for 4–9 November.

Worked charge calculation under the invented tariff
ChargeChargeable datesCalculationAmount
Demurrage6–8 Nov at first band; 9 Nov at second band3 × 90 + 1 × 140USD 410
Detention13–15 Nov at first band; 16 Nov at second band3 × 70 + 1 × 110USD 320
Terminal storage4–9 Nov, six days6 × 35USD 210
Total listed delay chargesSeparate clocks under these assumptions410 + 320 + 210USD 940

The full gate-out day participates in both equipment clocks under this invented convention. That is intentional for the exercise and must not be copied into a real calculation without confirming the actual rules. Calendar-day tariffs can also continue through days when a facility is closed, depending on the governing terms and applicable rules. Check rather than assume.

Compare an earlier collection and return plan

Under the same teaching tariff, suppose collection occurs on 5 November and empty return on 8 November. Demurrage is zero because gate-out occurs within its five free days. Detention is zero because return falls within 5–8 November, the four-day allowance. Storage still totals two chargeable days, 4 and 5 November, or USD 70.

The difference is USD 940 − USD 70 = USD 870 in listed delay charges. If an earlier accepted truck and unloading plan hypothetically costs USD 250 extra, the net reduction is USD 620. The operational choice remains conditional on release, truck availability, safe unloading and the nominated depot accepting the empty return; paying for an earlier truck is not useful if the container cannot be released.

Scenario comparison; all prices are teaching assumptions
PlanDelay chargesExtra expedited transport/unloadingCombined listed cost
Later collection/returnUSD 940USD 0USD 940
Earlier accepted collection/returnUSD 70USD 250USD 320
DifferenceUSD 870 lower delay chargesUSD 250 extra serviceUSD 620 lower combined cost

Compare a combined offer as an alternative, not an extra line

Compare combined equipment time with separate inside- and outside-terminal periods as alternative charge arrangements. This exercise uses the earlier fictional 1 November discharge, 9 November gate-out and 16 November empty return. Every rate and free allowance below is invented solely for the comparison.

Offer A is the earlier separate-clock example. Offer B instead allows ten calendar days of combined equipment time, from 1–10 November inclusive, and charges a fictional flat USD 100 for each subsequent day through the accepted return day. Offer B therefore has six chargeable days, 11–16 November. Assume the same separately billed USD 210 storage applies under either offer.

Alternative teaching offers for the same event dates
ChargeOffer A: separate clocksOffer B: combined clock
Demurrage and detention410 + 320 = USD 730Replaced by the combined charge
Combined equipment chargeNot applicable6 × 100 = USD 600
Separate storageUSD 210USD 210
Listed totalUSD 940USD 810
DifferenceReferenceUSD 130 lower in this example

Do not add Offer B’s USD 600 on top of Offer A’s USD 730. They are alternative equipment-charge arrangements, not simultaneous charges. The comparison assumes identical other services and no fee for the different allowance. A real offer may price extra free time separately, exclude different storage costs or use other events; include those differences before choosing.

Work through working-day free time and calendar-day charging

This independent date exercise uses an invented facility calendar: Monday–Friday are working days, there are no holidays, the discharge day counts if it is a working day, and four working days are free. Once the free period ends, a fictional USD 80 is charged for every calendar day through accepted empty return. This is a separate scenario; apply its stated counting rules only to this example.

Fictional mixed-calendar example in November 2026
Date or intervalTreatment in this exerciseResult
Friday 13 NovemberDischarge; first free working dayFree day 1
Saturday 14–Sunday 15Weekend during the free periodDo not consume a free working day
Monday 16–Wednesday 18Next three working daysFree days 2–4; last free date 18 November
Thursday 19–Monday 23Charge every calendar day; return on Monday 23 is counted5 days × USD 80 = USD 400

The weekend of 21–22 November is chargeable under this invented rule even though weekends did not consume the working-day allowance. That contrast is the point of the exercise. For an actual invoice, check holiday treatment, facility calendars, return acceptance, the precise charge start and any applicable exceptions. Count dates from those written rules rather than subtracting the free-day number from elapsed calendar days.

Prepare the receiving and return plan before arrival

Before arrival, verify the importing contact, documents, payment/release process, truck capacity, warehouse appointment and unloading equipment. For a container that needs several unloading days, compare a revised receiving plan or an approved transfer arrangement and its complete cost. Do not assume that an extra free day can be purchased retrospectively.

For empty return, save the nominated depot, receiving hours and any appointment or acceptance requirements. Retain instructions and evidence if a return attempt is rejected or the designated location is unavailable. Raise the issue promptly with the responsible party and request an alternative; keep the records needed to review any later charge.

Reconcile an invoice to event evidence

Match the container number, equipment type, tariff version, agreed free time and event timestamps. Reproduce each band separately and compare its days with gate or facility records. Where a charge is disputed, identify the precise date, rate or contract term rather than challenging an unexplained total.

Keep carrier equipment charges and facility storage on separate ledger lines until you establish how they interact. A dispute, waiver request or exceptional-event review is not an automatic cancellation. Record the amount as confirmed, queried or awaiting decision so the shipment budget remains transparent.

Use the fee clocks alongside a confirmed pickup and return plan. The US port-drayage guide compares live unloading, pre-pull and drop-and-pick operations for the same 40HC, including chassis days, driver waiting and empty-equipment return.

Plan collection and return before arrival

Send the booking details, container size, expected arrival, warehouse address and unloading arrangement. We can review the delivery scope, free-time records and return instructions needed for your shipment.

  1. Obtain the applicable tariff and any negotiated free-time confirmation for the actual booking.
  2. Record discharge, release, full gate-out and accepted empty-return events with their time basis.
  3. Confirm warehouse unloading and return-depot acceptance before approving the delivery plan.

Your checklist will be included in an editable quote request. Add your route and goods, then send it to our team by WhatsApp or email.